Update on summer refit

Final Top Coat goes on August 15th

Great progress since work started just 10 days ago, the final gel coat was applied today with just two days work left before the water can start to go back in. New drains have been added in the deep end to give a huge uplift in the water circulation to cope with the ever increasing demand for swimming tuition and coaching. All on target to open September 1st. You can see more pictures here: